View

Notice

Share

Regulatory Commission of Alaska: Notice of Utility Tariff Filing (ENSTAR)

Notice of Utility Tariff Filing

The REGULATORY COMMISSION OF ALASKA (Commission) gives notice that ENSTAR Natural Gas Company (ENSTAR) filed TA326-4, its annual revision to fees and allowances for installing new service connections, meters, and main line extensions. The new fees and allowances will be effective for calendar year 2022.

Service Line Installation Fee

ENSTAR proposes to increase its Basic Service Line Installation Fee for piping less than two inches from $764 per service line to $840 per service line.

Meter Installation Charges

The current and proposed rates are as follows:

Meter Size

Current

Proposed

G1

$277

$267

G2

$476

$457

G3 Low

$1,242

$1,186

G3 Mid

$2,115

$2,007

G3 High

$3,943

$3,917

G4 Low

$5,404

$5,589

G4 High

$6,079

$6,000

Meter sized greater than 5,000

Cost*

Cost*

*Cost includes materials, installations, and overheads

Standard Construction Cost

ENSTAR proposes to increase its Standard Construction Cost for the installed price of two-inch plastic main from $25.87 per foot to $28.46 per foot.

Standard Load Allowances

ENSTAR proposes revisions to the Average Load per Customer for the year 2022 to reflect a ten-year average. ENSTAR states that the ten-year average complies with the methodology that was used to calculate average loads in filings prior to the U-09-069 restructuring of rate classes. The current and proposed Standard Load Allowances are shown below. 

 

Embedded Cost

per Customer

Average Load

per Customer

Standard Load Allowance

per Mcf of Estimated Load

Customer Class

Current

Proposed

Current

Proposed

Current

Proposed

G1

$676

$713

143

143

$4.74

$4.97

G2

$1,709

$1,788

371

373

$4.60

$4.80

G3

$5,366

$5,505

1,169

1,173

$4.59

$4.69

G4

$32,655

$33,532

7,370

7,408

$4.43

$4.53

This notice does not contain all requested revisions and the Commission may approve a rate or classification which varies from that proposed. You may obtain more information about this filing by contacting Chelsea Guintu, Supervisor of Rates and Regulatory Affairs for ENSTAR, at P. O. Box 190288, Anchorage, AK 99519-0288; phone: (907) 277-5551. The complete filing is also available for inspection at the Commission's office at 701 West Eighth Avenue, Suite 300, Anchorage, AK 99501; phone: (907) 276-6222, or may be viewed at the Commission’s website at http://rca.alaska.gov by typing TA326-4 in the Find a Matter search box.

To comment on this filing, please file your comments by 5:00 p.m., June 2, 2021, at the Commission address given above or via our website at:

https://rca.alaska.gov/RCAWeb/WhatsNew/PublicNoticesComments.aspx

Please reference TA326-4 and include a statement that you have filed a copy of the comments with ENSTAR at its address given above. Individuals or groups of people with disabilities, who require special accommodations, auxiliary aids or service, or alternative communication formats, please contact Valerie Fletcher-Mitchell at (907) 276-6222, toll-free at 1-800-390-2782, or TTY/Alaska Relay: 7-1-1 or 1-800-770-8937, or send a request via electronic mail to rca.mail@alaska.gov by May 26, 2021.

DATED at Anchorage, Alaska, this 3rd day of May, 2021.

REGULATORY COMMISSION OF ALASKA

 

Becki Alvey

Tariff Section Manager

Attachments, History, Details

Revision History

Created 5/3/2021 11:12:48 AM by rtalabanzas

Details

Department: Commerce, Community and Economic Development
Category: Public Notices
Sub-Category: Pipeline/Utilities
Location(s): Statewide
Project/Regulation #:
 
Publish Date: 5/3/2021
Archive Date: 6/2/2021
 
Events/Deadlines:
  • Public Comment Deadline
    6/2/2021 5:00pm