View

Notice

Share

ITB Z642820000 Dalton Highway MP 89-90 Embankment Stabilization

Sealed bids for furnishing all labor, materials, equipment and performing all work on Project No. Z642820000, Dalton Highway MP 89-90 Embankment Stabilization, described herein, will be received until 2:00 p.m. prevailing time, July 19, 2018, in the Office of the Contracts Engineer, Engineering Services Building, Room 3, 2301 Peger Road, Fairbanks, Alaska.

The project consists of embankment stabilization, slope flattening, construction of a wayside pull off, drainage improvements, and application of dust palliative along approximately one mile of the Dalton Highway.

Engineer's Estimate is between $1,000,000 and $2,500,000.

The project completion date is October 31, 2018.

Plans, specs, bid documents, reports, addenda and other bidder information are posted online, available for downloading free of charge at: http://www.dot.state.ak.us/apps/contracts?ACTION=bidcal#46520.

Hard copies of plans & specifications are still available from the Contracts Section, Department of Transportation & Public Facilities, Engineering Services Building, Room 3, 2301 Peger Road, Fairbanks, Alaska 99709, telephone number (907) 451-2247; TDD (907) 451-2363 (for Hearing Impaired, requires special equipment).  There is a non-refundable charge of $100, per set.  Check or money order must be made payable to:  State of Alaska.

Bidding documents are available for inspection at the DOT&PF regional office in Fairbanks.

Attachments, History, Details

Attachments

None

Revision History

Created 6/27/2018 2:47:57 PM by plord

Details

Department: Transportation and Public Facilities
Category: Procurement
Sub-Category: Construction Bids
Location(s): Northern Region
Project/Regulation #: Z642820000
 
Publish Date: 6/28/2018
Archive Date: 7/31/2018
 